Crossrail C272 Paddington

Project Overview

  • Client Organisation: Crossrail
  • Client Contact: Carillion Plc
  • Sector: Rail / Building / Civil Engineering
  • Site Address: London
  • Value: £98 million
  • Contract: NEC3 Option C – Target Cost with Activity Schedule
  • Duration: 3 years construction

Adeo Staff

  • Quantity Surveyor – William Casey (Package Surveyor)
  • Senior Quantity Surveyor – Michael Meehan (Contract Change)
  • Managing Quantity Surveyor – Elliott Wickwar (Package Surveyor)
  • Quantity Surveyor – Martin Biu (Contract Change/Package Surveyor)

Image Gallery

Please click an image to expand:

Image gallery coming soon...

Summary of Scheme

The upgrade of the Northern section of Paddington Station as part a redevelopment of the whole station for the forthcoming Crossrail interchange to be opened in 2018. The works consisted of:

  • Redevelopment work to the London Underground Hammersmith & City and Circle Line Station including construction of new façade, redevelopment of the concourse and platform works
  • The construction of a new taxi ramp, a new plaza facing the Grand Union Canal and minor works to platform 12 of the main line station.

Role and Responsibilities

  • Procurement of sub-contract packages
  • Drafting sub-contracts orders for approval and issuing
  • Financial management of sub-contractors – including re-measuring works, certifying interim valuations, variations, issuing instructions, payment certification and final account agreements
  • Preparation, submission of Early Warning Notices (Main Contract)
  • Value and submit Compensation Events (Main Contract)
  • Change control management
  • Agreement and negotiation of Target Cost increase
  • Weekly / Monthly Cost forecast
  • Prepare internal cost reports and evaluate financial performance of contract on a weekly and monthly basis