Crossrail Stockley Airport Junction

Project Overview

  • Client Organisation: Crossrail/ Network Rail
  • Client Contact: Carillion Plc
  • Sector: Rail / Civil Engineering
  • Site Address: 192 Dawley Road, Hayes, UB3 1EH
  • Value: £37,000,000
  • Contract: ICE Network Rail 8 – Fixed Lump Sum
  • Duration: 3 years

Adeo Staff

  • Quantity Surveyor – Hugo Hardy (Change Control)

Image Gallery

Please click an image to expand:

Summary of Scheme

The principal objective of the project is the Civils Works associated with the Stockley Airport Junction scheme which will allow for the operation of the Crossrail fleet in the Stockley Airport Junction area. The overall scheme is to construct a viaduct approximately 1.5km long to carry the combined Up Airport Relief/Up Airport line form the Heathrow Spur. The viaduct structure will allow for the installation of a new elevated route for the Crossrail fleet and will curve across the running lines at its western end, then run parallel to the north of the railway, bifurcating into a Northern section (Up Airport Relief) and a southern section (Up Airport) re-crossing the Relief Lines.

Role and Responsibilities

  • Preparation and submission of Early Warning Notices
  • Value and submission of Contractor’s Requests for Change
  • Change control management
  • Weekly / Monthly Cost forecast
  • Preparation of monthly reports