Olympic Park - Wetlands

Project Overview

  • Client Organisation: Land & Water Services Limited
  • Sector: Civil Engineering / Landscaping
  • Site Address: 2012 Olympic Park – North Park River Lea
  • Value: £2.2 million (NEC Option C – Target Cost)
  • Duration: 80 weeks

Adeo Staff

  • Managing Quantity Surveyor – Brent Maartens
  • Planner – Hamid Chughtai
  • Document Controller, Quantity Surveyor – Philip Landman
  • Document Controller, Quantity Surveyor – Tristan Webb

Image Gallery

Please click an image to expand:

Role and Responsibilities

  • Monthly Valuations submitted to the Main Contractor – (BAM Nuttall)
  • Monthly Earned Value / Planned Value Analysis against the programme
  • Monthly Programmes for acceptance
  • Programmes for Early Warnings / Compensation Events
  • Cash Flow Forecasts
  • Identifying and raising Early Warnings and Compensation Event Notices in order to produce Compensation Events for implementation
  • Picking up changes that occurred against the contract and pricing those changes
  • Reporting to Land & Water's Commercial Manager on a weekly basis re: Target Cost movement
  • Resolving contractual differences and agreeing Compensation Events with the Main Contractor
  • Managing the document control for all documents using Business Co-ordinator
  • Managing the booking in of deliveries and site passes through ODA security
  • Managed all commercial aspects to the clients' expectations to ensure that the client maximised the potential of achieving the target cost or below
  • Managed all documents to ensure that actual costs were easily auditable and that there were no delays in deliveries and labour gaining access into the site to work
  • Continuous monitoring and production of programme to ensure that key dates were achieved